Home » Our projects » Completed Projects » AUTOLIB (Multi-site Project)
Client : |
The City of Paris BOLLORE Group
|
Location : |
Ile de France (Paris and Greater Paris)
|
Surface area : |
1098 Stations
|
Duration : |
11 months
|
Phase 1 deadline : |
December 2011 (public opennig) |
Final Deadline : |
June 1st 2012
|
Projexia's Mission : |
Construction Management for the: • Project
planning and scheduling
•
Construction works monitoring and
coordination
|
Project Description: |
Realization of 1048 stations for Paris electric car sharing program |
Project Challenges : |
The important number of stations, spread out all over the city and the surrounding cities, and the very short timeframe, require rigorous project management methods in order to maintain the tight schedule, budget and quality of the work executed. |